Project Summary

Product: Fire alarm, CCTV, access control, intercom, DDA, intruder
Total value: £105,000
Programme: 41 weeks
Project type: Commercial offices

This project comprised of the refurbishment and extension of an existing office structure.

The fire alarm and DDA services installed were to provide safety and protection for both the building and all personnel within the offices. Fully networked disabled toilet alarm system integrated with the disabled refuge system for the site was designed to ensure the latest DDA requirements were met.

A comprehensive access control and intercom system had to be designed and developed by us to enable the individual offices the capability to have multiple tenancy with global integration. The CCTV system design was to provide a strong perimeter protection with remote viewing from anywhere in the world for multiple tenants broken down into their individual access areas.